Week 33  This week we get yet more forward superstructure

The bits we received

And what we did with them

This week was very straight forward.   I glued the parts in the photo below first.  Of course, everything was dry fitted first, and keep everything square.

You can get parts to fit tighter together by chipping off the inside corner where they fit into a slot.

Once everything was dry Kilroy fitted the top part 171.

And then he screwed the last four bulkheads in place.

Things not yet done

Stern planking
Fitting the fore deck
Stern deck part 63 not fitted.
Resin bow piece 67 not fitted
Fixing deck

Hot tip of the week

Lots of test fitting and making sure things are square makes for a better model

How many hours does it take to build the model ??

This week :

2 hrs

Running total :

108 hrs